GESO SYSTEMS' commissioning service:
Nanjing U-BASE Automation System Co., Ltd.
BLT-100AG/10.5*1 set
Start-up and commissioning completed, the machine is running normally. Due to the problem of the customer's electrical box, the power supply is delayed. The nitrogen generator outlet and compressed air outlet are installed. At present, the customer's gas requirements are met first, and Gateway installation and personnel training will be carried out later. The customer leaves work on time and signs the startup and commissioning form next time.